Speaking today, 12 February 2019, Minister for Finance and Public Expenditure and Reform, Paschal Donohoe TD, outlined how the €99m necessary this year for the timely provision of the National Children’s Hospital will be accommodated with a minimum of disruption to the scheduled rollout of key infrastructure projects under Project Ireland 2040. The Minister also detailed reforms that are designed to ensure world class project management across the whole of Government.
Ensuring Delivery
Speaking post Cabinet, the Minister said
The National Children’s Hospital is a vital and much needed project. It is the most significant healthcare investment ever undertaken by the State, one that will have an impact on children, young people and their families in Ireland for decades to come.
In meeting these funding pressures we have examined all our projects and programmes across government. Where projects are, due to external issues, paused such as in the case of A5 Motorway in Northern Ireland, we moved those currently unused funds to where they are needed now. Where the timing of drawdown of payments could be updated without jeopardising the pace of project planning, design and delivery, we have made adjustments to ensure that the much-needed National Children’s Hospital will be delivered.
Therefore, in Health the scheduled draw-down of €24m across both 2019 and 2020 will be amended to facilitate delivering the overall investment programme, as set out in Project Ireland 2040. This adjustment will still leave a year-on-year increase of 25% in capital investment in the Health sector in 2019.
The remaining €75m will be met by:
Project Delivery Reforms
The Minister added:
Project Ireland 2040 has already delivered major projects including the Luas Cross City and the M17 Gort to Tuam motorway which dramatically improves road access along the western coast. We are continuing important investment programmes for roads and light rail, improving our environment, with 90 new schools under construction in 2019 and 700 benefiting from minor improvements. Investment will provide 10,000 social housing units and support better health outcomes with primary care facilities to be opened or upgraded in 18 locations nationwide. We are undertaking enormous investment and we have made much progress delivering projects on time and on budget but it is clear that the experience of the National Children’s Hospital must be drawn upon, and lessons learned, to ensure that this type of cost overrun is avoided in future and so our project management procedures keep pace and are world-class.
As a result we are speeding up the reforms to our public procurement process which were put in train as part of Project Ireland 2040. These include the below:
In the future, the budgets for large bespoke projects will include a significant premium for risks so that these indicative costings more adequately reflect the holistic total for the entire project over its lifecycle.